Large Cornice pieces were secured by the end of day 2. Panels of sheet copper were affixed to the roof (or floor, if you’re standing on it!) of the balcony, and then the joints individually soldered by hand. Again, 94+ degree temps made the day a long and tiresome one for Grand River’s employees.
Balcony Installation Progress
Day 1 of Grand River’s installation schedule yielded significant progress on the balcony. The main piece and frame was affixed to the building and several additional pieces were attached. They worked in 96+ degree heat throughout the day.
Grand River Builders Arrives With Balcony Pieces
On June 21, 2022 Grand River Builders arrived with all of the custom fabricated copper pieces of the balcony. Each individual piece was made to fit together perfectly, and every single individual piece of copper was hand-crafted and hand-soldered together.
Door Restoration & Recreated Wood Panels
Kirk @ Sphere Project Management took off the two dry rotted doors on the north stairwell and took them back to his shop to fully restore them. All of the wood below the glass was fully replaced with reclaimed wood from the 1800s, all the brass hardware was removed, cleaned, polished, and internals cleaned and lubricated. In addition, a wood panel that was missing was refabricated from scratch to match the original panels beneath the rest of the storefront windows and installed.
Next Steps…
Next steps to be completed in 2022
- Re-fabricated Balcony Installation (In progress)
- Additional downspout work
- Replacement of several wooden trim pieces on front façade (In progress)
- Masons – replace damaged brick and tuckpoint entire front façade
We’re not sure if we’ll get to painting trim in 2022.
Stripping Completed
On June 10, 2022, Stripping the paint from the brick was completed. The remaining white spots will be removed by the Masons – it’s mostly patching and caulk.
Continued Stripping Progress
Throughout May and into June, Lenco slowly stripped off the paint.
Chemical Stripping Progress
Throughout May and early June, progress continued as we peeled back 6-8 layers of paint. Certain areas required 6 applications of stripper.
Stripping the Front Façade
In May, 2022, Lenco Painting began to chemically strip the front of the building.
Balcony Update
Grand River Builders sent us this photo of the balcony fabrication in-progress.